Jamshedpur: Tata Power, one of India’s largest integrated power companies, has successfully commissioned the second phase of its Jalpura-Khurja transmission project in Uttar Pradesh. This move will further strengthen the state’s power transmission infrastructure, ensuring improved supply to areas in the NCR and Western Uttar Pradesh that are witnessing rapidly growing electricity demand.
The project has been executed through TP Jalpura Khurja Power Transmission Limited (TPJKPTL), a wholly-owned subsidiary of Tata Power. Under this second phase, a 162-circuit-kilometer (CKM) long 400 kV double-circuit transmission line connecting Khurja to Jalpura and a 1,000 MVA capacity 400/220 kV GIS substation at Jalpura have been commissioned.
Also Read: On November 16, Delhi Metro will begin operations for Chhath Puja at 4:30 AM
This 162 CKM transmission corridor comprises two circuits of approximately 81 kilometers each, establishing a vital high-voltage link between Khurja and Jalpura. As Khurja is a key power hub in Western Uttar Pradesh, this corridor will play a crucial role in ensuring the efficient and uninterrupted supply of electricity from Khurja to Noida and the wider NCR region.
The newly commissioned 1,000 MVA capacity 400/220 kV GIS substation at Jalpura will serve as a major power gateway, enabling the transfer of electricity from the 400 kV high-voltage grid to the 220 kV network. This initiative will help meet the region’s rising power demands by enhancing the capacity, reliability, and efficiency of the transmission network. With the commissioning of this new transmission corridor and substation, Tata Power has further strengthened the power infrastructure essential for sustaining the pace of development in the NCR and Western Uttar Pradesh. This initiative contributes significantly to the broader goal of building a robust and modern electricity grid for the nation. The project demonstrates Tata Power’s capability to execute large-scale power infrastructure developments and reaffirms its commitment to making India’s transmission network more reliable, resilient, and future-ready.
With this addition, Tata Power’s transmission portfolio now spans 7,900 circuit kilometers of operational and under-construction lines across India. This further reinforces the company’s leading role in strengthening the nation’s power supply infrastructure.
Also Read: 96.47 kg Ganja Seized at Assam-Arunachal Border, Vehicle Driver Absconds
Related News
- National On November 16, Delhi Metro will begin operations for Chhath Puja at 4:30 AM
- National 96.47 kg Ganja Seized at Assam-Arunachal Border, Vehicle Driver Absconds
- National On Diwali Eve, Ayodhya lights up the Sarayu Ghats with 30 lakh diyas as Deepotsav festivities get underway
- National CBSE Date Sheet 2027: Will the Board Modify the Dates of the Five Class 12 Exams Set for Holi?